Shipping two SC200/200 hoists in one 40HQ

2026-11-16 09:00:00 Company news

A 180 m SC200/200 needs 119 mast sections per machine. Two machines is 238 sections plus four cages, six drive units and the electrical cabinets — and buyers regularly ask whether that fits in one 40HQ. It does not. Here is the arithmetic we use when we issue a loading plan.

Mast sections: the container maths

A 40HQ gives roughly 12.03 × 2.35 × 2.69 m of internal space. A 650 × 650 × 1508 mm section, stood on end:

  • Length: 12,030 / 1,508 = 7 rows
  • Width: 2,350 / 650 = 3 columns
  • Height: 2,690 / 650 = 4 layers

That is 84 sections in a clean cube — about 32 tonnes, which already exceeds the 26–28 t payload most carriers allow on this route. Weight, not volume, is the binding limit on mast sections.

The plan for two machines

ContainerContentsApprox. weight
184 mast sections28 t
284 mast sections28 t
370 mast sections + 4 cages (nested) + 6 drive units27 t
42 tie-in sets, base frames, electrical cabinets, spares box18 t

Four 40HQ for two 180 m hoists is the honest answer, and the fourth container runs light — that is where we consolidate tie-ins, base sections and the two-year consumables kit rather than adding sections and overloading it.

How the cages travel

Cages ship knocked down: floor frame, two side panels, roof, door assembly and the safety device removed and boxed. Two cages nest into the footprint of one, which is why they ride in container 3 between mast section stacks instead of taking a container of their own. Glass and electricals always travel in a separate crate, never inside the cage.

Securing the load

  • Mast sections stood vertically in three columns, timber dunnage between layers.
  • Steel strapping at four heights per column, not rope.
  • Heaviest items over the container axles, never at the doors.
  • Doors blocked with timber so nothing shifts against the seals in transit.
  • Photographs of the loaded container before the doors close — this is the only evidence that survives a damage claim.

Documents that ship with the container

Packing list with section-level quantities, commercial invoice, bill of lading, certificate of origin, and per-unit certificates for the anti-fall devices. The load chart and foundation drawing travel in the document pouch, not inside a crate — customs and the erection crew both need them early.

Frequently asked

Can you fit one 180 m hoist in a single 40HQ? No. One machine is 119 sections, about 40 t — one and a half containers at legal payload.

Is a 40HQ better than a 40GP? For mast sections, no. The 300 mm of extra height does not add a fifth layer, and the higher cube costs more.

How long does loading take? Four to six hours for a full mast container with a forklift and two riggers.

Related: SC200/200 hoist · 650 × 650 mast section · drive unit

← Back to list Request a quote
Mast line upgraded with a second robotic welding cell

Send the site data, get a configuration and a price

Building height, required payload and power supply are enough for us to come back with a model, a drawing and a delivered price within one working day.

15688868277